Project

General

Profile

Actions

Task #111

open
SG SG

Task #110: Weekly GP Dashboard: rebuild as Frappe Page (local, FTWZ data)

Web Page dashboard upgrade (07/10)

Task #111: Web Page dashboard upgrade (07/10)

Added by Srishti Ghosh 14 days ago. Updated 8 days ago.

Status:
New
Priority:
Normal
Assignee:
Target version:
-
Start date:
10/07/2026
Due date:
10/07/2026 (15 days late)
% Done:

100%

Estimated time:
Spent time:

Description

Work done on the existing Weekly GP Web Page (/gp-dashboard, SLCPL data-migration site) before the Frappe Page rebuild.

  • Added filters, summary cards, charts and a branch report below the original weekly table
  • Restored the original table after the first version replaced it; kept its drill-down (week → branch → project type) unchanged
  • Charts use the FY week numbers and targets from the original script (shared via window.GP_DASHBOARD_CONFIG)
  • Visual refresh: card layout, spacing, fonts, chart styling (table + new section styled as one design)
  • Reorganised into tabs: Overview / Targets / Branches / Project types / Reports
  • Added headline strip, this-week boxes, target-status colours on branch bars, branch and Mumbai-group target progress, project type report with CSV
  • Security: get_gp_dashboard_data server script now checks the "33-Weekly GP report" role
  • Each change previewed locally with sample data before being pasted into the site
Actions

Also available in: PDF Atom